It seems that using the "Change Shown Visualization" option on a mouse down event changes the visualization for all connected clients to the target visualization instead of change it only for the client that had the mouse down event. Is there a different way to switch between visualizations so-as not to affect other clients?
If you would like to refer to this comment somewhere else in this project, copy and paste the following link:
SOLUTION: Found that "Use CurrentVisu variable" in the General Settings tab of the VisualizationManager got checked. Unchecking this option let the clients operate independently.
π
1
If you would like to refer to this comment somewhere else in this project, copy and paste the following link:
IDE: 3.5 SP17 Patch 2
Runtime: Win V3 X64 3.5.17.20
It seems that using the "Change Shown Visualization" option on a mouse down event changes the visualization for all connected clients to the target visualization instead of change it only for the client that had the mouse down event. Is there a different way to switch between visualizations so-as not to affect other clients?
SOLUTION: Found that "Use CurrentVisu variable" in the General Settings tab of the VisualizationManager got checked. Unchecking this option let the clients operate independently.