Sfc Active step

2017-02-07
2017-02-09
  • josepmariarams - 2017-02-07

    Hi

    There exist a string variable in sfc which has the name of the active step. But if there are more than one step active, only has the righter one.

    Anyone knows if in future versions we can know all active steps?

     
  • r.evbatyrov - 2017-02-09

    Hi Josep,

    currenlty that is not implemented.
    There is a proposal
    CDS-32102 SFC: SFCCurrentStep : solution for parallel steps
    but it is not actually planned.

    Regards
    Roman

     