When I onlinechange the program i very often get 'OnlineChange failed no task gap within 1000ms: [Application] '. The PLC goes in to STOP and then I am able to download. What am I doing wrong?
Kind Regards,
Thomas
If you would like to refer to this comment somewhere else in this project, copy and paste the following link:
Hello,
When I onlinechange the program i very often get 'OnlineChange failed no task gap within 1000ms: [Application] '. The PLC goes in to STOP and then I am able to download. What am I doing wrong?
Kind Regards,
Thomas
I've found out what the problem causes. My 3 tasks where defined with the same priority. Now i changed this I have no problems anymore.
ok, because never seen this...!
thanks for the feedback well appreciated.
BR
Edwin